Kamis, 03 Mei 2018

Sponsored Links

Thames Barrier - Wikipedia
src: upload.wikimedia.org

The Thames Barrier prevents the floodplain of most of Greater London from being flooded by exceptionally high tides and storm surges moving up from the North Sea. It has been operational since 1984. When needed, it is closed (raised) during high tide; at low tide it can be opened to restore the river's flow towards the sea. Built approximately 3 km (1.9 mi) due east of the Isle of Dogs, its northern bank is in Silvertown in the London Borough of Newham and its southern bank is in the New Charlton area of the Royal Borough of Greenwich.

The report of Sir Hermann Bondi on the North Sea flood of 1953 affecting parts of the Thames Estuary and parts of London was instrumental in the building of the barrier.


Video Thames Barrier



History

Design and construction

The concept of the rotating gates was devised by (Reginald) Charles Draper. In 1969, from his parents' house in Pellatt Grove, Wood Green, London, he constructed a working model. The novel rotating cylinders were based on the design of the taps on his gas cooker. The barrier was designed by Rendel, Palmer and Tritton for the Greater London Council and tested at the Hydraulics Research Station, Wallingford. The site at New Charlton was chosen because of the relative straightness of the banks, and because the underlying river chalk was strong enough to support the barrier. Work began at the barrier site in 1974 and construction, which had been undertaken by a Costain/Hollandsche Beton Maatschappij/Tarmac Construction consortium, was largely complete by 1982. The gates of the barrier were made by Cleveland Bridge UK Ltd at Dent's Wharf on the River Tees.

In addition to the barrier, the flood defences for 11 miles down river were raised and strengthened. The barrier was officially opened on 8 May 1984 by Queen Elizabeth II. Total construction cost was around £534 million (£1.6 billion at 2016 prices) with an additional £100 million for river defences.

Built across a 520-metre (570 yd) wide stretch of the river, the barrier divides the river into four 61-metre (200 ft) and two, approximately 30 metre (100 ft) navigable spans. There are also four smaller non-navigable channels between nine concrete piers and two abutments. The flood gates across the openings are circular segments in cross section, and they operate by rotating, raised to allow "underspill" to allow operators to control upstream levels and a complete 180 degree rotation for maintenance. All the gates are hollow and made of steel up to 40 millimetres (1.6 in) thick. The gates are filled with water when submerged and empty as they emerge from the river. The four large central gates are 20.1 metres (66 ft) high and weigh 3,700 tonnes each. Four radial gates by the riverbanks, also about 30 metres (100 ft) wide, can be lowered. These gate openings, unlike the main six, are non-navigable.

Predictions for operation

A Thames Barrier flood defence closure is triggered when a combination of high tides forecast in the North Sea and high river flows at the tidal limit at Teddington weir indicate that water levels would exceed 4.87 metres (16.0 ft) in central London. Though Teddington marks the Normal Tidal Limit, in periods of very high fluvial flow the tidal influence can be seen as far upstream as East Molesey on the Thames.

Barrier closures and incidents

During the barrier's entire history up to October 2017, there have been 179 flood defence closures. The barrier was closed twice on 9 November 2007 after a storm surge in the North Sea which was compared to the one in 1953. The main danger of flooding from the surge was on the coast above the Thames Barrier, where evacuations took place, but the winds abated a little and, at the Thames Barrier, the 9 November 2007 storm surge did not completely coincide with high tide.

On 20 August 1989, hours after the Marchioness disaster, the barrier was closed against a spring tide for 16 hours "to assist the diving and salvage operations".

The barrier has survived 15 boat collisions without serious damage.

On 27 October 1997, the barrier was damaged when the dredger MV Sand Kite, operating in thick fog, hit one of the Thames Barrier's piers. As the ship started to sink she dumped her 3,300 tonne load of aggregate, finally sinking by the bow on top of one of the barrier's gates where she lay for several days. Initially the gate could not be closed as it was covered in a thick layer of gravel. A longer term problem was the premature loss of paint on the flat side of the gate caused by abrasion. The vessel was refloated in mid-November 1997.

The annual full test closure in 2012 was scheduled for 3 June to coincide with the Thames pageant celebrating Queen Elizabeth II's Diamond Jubilee. Flood risk manager Andy Batchelor said the pageant gave the Environment Agency "a unique opportunity to test its design for a longer period than we would normally be able to", and that the more stable tidal conditions in central London that resulted would help the vessels taking part.

Ownership and operating authority

The barrier was originally commissioned by the Greater London Council under the guidance of Ray Horner. After the 1986 abolition of the GLC it was operated successively by Thames Water Authority and then the National Rivers Authority until April 1996 when it passed to the Environment Agency.


Maps Thames Barrier



Future

The barrier was originally designed to protect London against a very high flood level (with an estimated return period of one hundred years) up to the year 2030, after which the protection would decrease, while remaining within acceptable limits. At the time of its construction, the barrier was expected to be used 2-3 times per year. It is now being used 6-7 times per year.

This defence level included long-term changes in sea and land levels as understood at that time (c. 1970). Despite global warming and a consequently greater predicted rate of sea level rise, recent analysis extended the working life of the barrier until around 2060-2070. From 1982 until 19 March 2007, the barrier was raised one hundred times to prevent flooding. It is also raised monthly for testing, with a full test closure over high tide once a year.

Released in 2005, a study by four academics contained a proposal to supersede the Thames Barrier with a more ambitious 16 km (10 mi) long barrier across the Thames Estuary from Sheerness in Kent to Southend in Essex.

In November 2011, a new Thames Barrier, further downstream at Lower Hope between East Tilbury in Essex and Cliffe in Kent, was proposed as part of the Thames Hub integrated infrastructure vision. The barrier would incorporate hydropower turbines to generate renewable energy and include road and rail tunnels, providing connections from Essex to a major new hub airport on the Isle of Grain.

In January 2013, in a letter to The Times, a former member of the Thames Barrier Project Management Team, Dr Richard Bloore, stated that the flood barrier was not designed with increased storminess and sea level rises in mind, and called for a new barrier to be looked into immediately. The Environment Agency responded that it does not plan to replace the Thames Barrier before 2070, as the barrier was designed with an allowance for sea level rise of 8 mm per year until 2030, which has not been realised in the intervening years. The barrier is around halfway through its designed lifespan. The standard of protection it provides will gradually decline over time after 2030, from a 1 in 1000 year event. The Environment Agency are examining the Thames Barrier for its potential design life under climate change, with early indications being that subject to appropriate modification, the Thames Barrier will be capable of providing continued protection to London against rising sea levels until at least 2070.


the Barrier, Thames Rockets Speed Boat Ride for Two
src: www.virginexperiencedays.co.uk


In popular culture

  • McCallum, a British television series that was produced by STV Productions (Scottish Television) and ran from 1995 to 1998 showed an aerial fly over of the Thames Barrier at night, during the opening and closing credits.
  • The 1986 rock music video for "Cross That Bridge" by UK Band "The Ward Brothers" was filmed both inside & outside Thames Barrier #1.
  • In the 1982 Alexei Sayle track "'Ullo John! Gotta New Motor?" the barrier is mentioned in the lyrics, "He works on the Thames barrier - he works on the Thames barrier!"
  • The climax of Lois McMaster Bujolds 1989 novel Brothers in Arms takes place in and near the Thames Barrier.
  • In series 5 episode 7 (1992) of firefighting drama London's Burning, Blue Watch are called to the Thames Barrier to rescue a maintenance worker.
  • In the tenth episode of Series 5 of Spooks, broadcast in mid-late-2006 an environmental group threatens to blow up the Thames Barrier.
  • The Thames Barrier appears in the 2006 Doctor Who Christmas special, "The Runaway Bride". The Doctor and his companion Donna Noble emerge from the barrier after defeating the Empress of the Racnoss and her children by flooding her secret underground lair, only to find out that they have accidentally drained the Thames.
  • In 2007 in season 10, episode 5 of Top Gear co-host Jeremy Clarkson drives a racing boat through the Thames Barrier while racing James May, Richard Hammond, and The Stig to London City Airport.
  • The barrier features as one of the main locations of Flood, a 2007 British disaster film, directed by Tony Mitchell It features Robert Carlyle, Jessalyn Gilsig, David Suchet and Tom Courtenay. It is based on the 2002 novel of the same name by Richard Doyle.
  • The barrier features near the end of the music video for Take That's 2010 hit single, "The Flood".

TESTING, TESTING: Thames Barrier Closure on Sunday â€
src: charltonchampion.files.wordpress.com


Gallery


The Thames Path - The Thames Barrier to Crayford
src: www.thames-path.org.uk


See also

  • Barrier Gardens Pier
  • Delta Works with the Oosterscheldekering
  • Floodgate
  • MOSE Project
  • Saint Petersburg Dam Flood Prevention Facility Complex
  • Crossings of the River Thames

London-Under-Sea
src: www.suug.co.uk


References


aerial view of The Thames Barrier in East London Stock Photo ...
src: c7.alamy.com


Further reading

  • Stuart Gilbert and Ray Horner. The Thames Barrier Telford 1984 ISBN 0-7277-0249-1
  • S Gilbert. The Thames Barrier. Thomas Telford Ltd. 30 June 1986. 216 pages. ISBN 0-7277-0249-1.
  • Ken Wilson. The Story of the Thames Barrier. Lanthorn. 1984. 32 pages. ISBN 0-947987-05-3.

Thames Barrier - Great Attractions (United Kingdom) - YouTube
src: i.ytimg.com


External links

  • Thames Barrier page at the Environment Agency
  • Animation showing how the Barrier works
  • "Time-lapse video showing Thames Barrier operating in flood conditions". Daily Telegraph. 5 January 2014. 
  • Streetmap of Thames Barrier
  • Thames Barrier Information and Learning Centre - on south side of the Thames
  • Thames Barrier Park - park by the Barrier on north side of the Thames
  • Londons flood defence system
  • Map of associated flood barriers
  • Risques VS Fictions n°8, filmed interview (subtitled in French) with Steve East, technical support team leader of the real barrier about the depiction of the barrier and scientific accuracy of Flood.

Source of the article : Wikipedia

Comments
0 Comments